进行地基强夯如何解决地下水的影响问题

网址:http://www.sddhfjx.cn/   发布日期:2022-05-06 关注次数:0
强夯地基施工会遭到很多要素的影响,这些要素都会影响地基强夯施工的结果,施工的进度等等。强夯地基在施工中怕的就是遭到地下水的影响,一些处所的水位比较低,在地基处置施工的进程中就会呈现出水的现象。还有一种就是施工对点本身就有水,需要短光阴之内排水等等。这对强夯地基都是有一定的影响的,下面强夯为你详细解说一下两种办法的处置办法。地下水对强夯地基有哪些影响?
Dynamic compaction foundation construction will be affected by many factors, which will affect the results and progress of foundation dynamic compaction construction. The fear of dynamic compaction foundation in construction is that it will be affected by groundwater. The water level in some places is relatively low, and water will appear in the process of foundation disposal construction. Another is that the construction point itself has water, which needs to be drained in a short time, etc. This has a certain impact on the dynamic compaction foundation. The following dynamic compaction will explain the disposal methods of the two methods in detail. What are the effects of groundwater on dynamic compaction foundation?
1、施工场地内有积水
1. There is ponding in the construction site
假设是短光阴之内的积水还利益理,只要是抽干积水然后稍微晾干就可能操作了。例如一些雨季在一些低洼的地带会呈现相似的问题;假设是积水光阴比拟长,就需要提早停止排水,尽量减低积水对强夯地基的影响。给水处置之后假设是由淤泥的状况下需要停止淤泥的消弭,这个需要提早处置好,为强夯地基供应一个好的施工环境。
Assuming that the accumulated water in a short time is reasonable, it may be operated as long as the accumulated water is drained and then dried slightly. For example, some rainy seasons will present similar problems in some low-lying areas; Assuming that the ponding time is relatively long, it is necessary to stop drainage in advance to minimize the impact of ponding on dynamic compaction foundation. After water supply treatment, it is assumed that the elimination of sludge needs to be stopped under the condition of sludge, which needs to be disposed in advance to provide a good construction environment for dynamic compaction foundation.
2、强夯之后出水:这是由于公开水位比拟低形成的,个别在秋季跟冬季随便呈现。处理的方法就是可能在周边挖几个排水井,这样积水可能顺着水渠排入排水井,然后再排出场地之外。
2. Water after dynamic compaction: This is due to the relatively low open water level, which is casually presented in autumn and winter. The treatment method is to dig several drainage wells around, so that the accumulated water may be discharged into the drainage wells along the canal, and then discharged out of the site.
以上就是为大家介绍的有关强夯机出租http://www.sddhfjx.cn的详细的介绍,希望对您有所帮助.如果您有什么疑问的话,欢迎联系我们.我们将以的态度,为您提供服务
The above is about the rental of dynamic compaction machine http://www.sddhfjx.cn I hope it will be helpful to you If you have any questions, please contact us We will provide you with professional service